Moorebank Avenue Realignment start of work – 20 January 2025
Tuesday 14th January 2025
As part of the Moorebank Intermodal Precinct project, the Moorebank Avenue Realignment Works (MARW) will start on 20 January 2025.
MARW involves the realignment of an existing two kilometre section of Moorebank Avenue, from approximately 130 metres south of the existing Anzac Road/Moorebank Avenue intersection to immediately north of the East Hills Railway. This will be constructed as a new two lane road, east of the existing Moorebank East Precinct, and is expected to have minimal impact on existing traffic arrangements.
What to expect
On Monday 20 January 2024, weather permitting, there will be changes within Moorebank Intermodal Precinct.
Work will involve:
• Establish temporary construction compound and site utilities
• Establish temporary fencing and exclusion zones and demarcation of work site
• Traffic management measures such as safety barriers and signage
• Temporary environmental safeguards such as erosion, sediment, and water quality controls
• Site investigation
• Adjustment and relocation of utilities.
This work will take place within the Moorebank Intermodal Precinct, with no impact to road users. We will require the use of light vehicles, excavators, rollers, bobcat, compaction equipment, bogie trucks and heavy vehicles.
We apologise for any inconvenience this may cause.
Where & when
Moorebank Precinct East Standard Construction hours
7.00am – 6.00pm – Monday to Friday
8.00am – 1.00pm – Saturdays
Keeping you updated
Work notifications are published on the project website at www.moorebank.au. We encourage community members and interested stakeholders to register for project updates to receive notification updates by email. Please contact our Community Relations team on the details below or opt-in for emailed updates by completing the form on our website.
Contact us
We appreciate your cooperation and patience while these important works are undertaken. If you have any queries about this work or would like to speak with a member of the project team, please contact us via email moorebank@tsamgt.com or by phone 1800 986 465 (24/7).