Construction Roadworks April 2025

Current Works
Friday 4th April 2025

To support the Moorebank Intermodal Precinct (MIP), the Moorebank Avenue Realignment Works (MARW) Project Contractor, BMD, will start construction works from early April 2025.

Where & when

Moorebank Avenue Realignment Footprint
Standard Construction hours
7.00am – 6.00pm Monday to Friday
8.00am – 1.00pm Saturdays

About the project
MARW involves the realignment of an existing three-kilometre section of Moorebank Avenue, from approximately 130 metres south of the existing Anzac Road/Moorebank Avenue intersection to immediately north of the East Hills Railway. This will be constructed as a new four-lane/two-lane road, east of the existing Moorebank Precinct East, and once operational will improve vehicle access for public and operational vehicles.

The majority of construction works for the MARW will be offline, with minimal impact on existing traffic arrangements expected.

What to expect

From early April 2025 weather permitting, construction works within the MARW footprint will include, but are not limited to:

• Installing traffic management controls and access gates
• Traffic staging and switches
• Construction of temporary and permanent water basins
• Stormwater drainage works
• Site clearing and remediation
• Earthworks and materials importation
• Construction of retaining walls
• Utility adjustment and relocation works
• Demolition and removal of redundant utilities
• Removal of the Disused Rail Spur (DURS)
• Traffic signal installation
• Kerb, gutter and median installation
• Asphalt works
• Fencing and road barriers
• Streetlighting
• Shared path construction
• Linemarking and sign posting
• Landscaping

Works will take place around the Moorebank Intermodal Precinct, with limited impact to road users. Equipment such as light vehicles, profilers, excavators, rollers, bobcats, compaction
equipment, bogie trucks, cranage, and heavy vehicles will be required.

We apologise for any inconvenience this may cause.

View or download the notification here.

Recent Media Releases
  • Current Works

  • 4 April 2025

Anzac Road closure & traffic switch April 2025

To support the Moorebank Intermodal Precinct (MIP), the Moorebank Avenue Realignment Works (MARW) Project Contractor, BMD, will start construction works from early April 2025. Where & when Moorebank Avenue Realignment Footprint Standard Construction hours 7.00am – 6.00pm Monday to Friday 8.00am – 1.00pm Saturdays About the project MARW involves the realignment of an existing three-kilometre […]

Read More
  • 26 March 2025

Out of hours work – April to June 2025

To support the Moorebank Intermodal Precinct (MIP), the Moorebank Avenue Realignment Works (MARW) Project Contractor, BMD, will start construction works from early April 2025. Where & when Moorebank Avenue Realignment Footprint Standard Construction hours 7.00am – 6.00pm Monday to Friday 8.00am – 1.00pm Saturdays About the project MARW involves the realignment of an existing three-kilometre […]

Read More
  • 10 March 2025

Track Maintenance and Signal Commissioning at Moorebank Intermodal Precinct

To support the Moorebank Intermodal Precinct (MIP), the Moorebank Avenue Realignment Works (MARW) Project Contractor, BMD, will start construction works from early April 2025. Where & when Moorebank Avenue Realignment Footprint Standard Construction hours 7.00am – 6.00pm Monday to Friday 8.00am – 1.00pm Saturdays About the project MARW involves the realignment of an existing three-kilometre […]

Read More