Out of Hours Works on 30 October – 6 November 2023
Thursday 26th October 2023
As part of the Moorebank Intermodal Precinct project, out of hours works will commence on 30 October – 6 November 2023.
Project contractor, John Holland Rail, will be undertaking rail lengths movement at Moorebank Precinct West.
This work scope is part of the critical work requirements to establish the new interstate rail line at Moorebank Intermodal Precinct.
Extended works are scheduled between 5:00 pm and 6:00 am 30 October – 6 November 2023.
The works have been scheduled outside of regular construction hours to manage site safety risks associated with the movement of large structures across the site.
Any changes to this scheduled delivery will be published on the Project website at moorebank.au
What to expect
This work will create moderate additional background noise.
We apologise for any inconvenience if caused.
Where & when
Moorebank Intermodal Precinct West.
Monday, 30 October 2023 to Monday, 6 November 2023 5:00 pm – 6:00 am.
Any changes to this scheduled delivery will be published on the moorebank.au website.
Keeping you updated
Work notifications are published on the project website moorebank.au
We encourage community members and interested stakeholders to register to receive project updates by email. Please contact our Community Relations team on the details below or opt-in for email updates by completing the form on our website.
Contact us
We appreciate your patience while these important works are undertaken.
If you have any queries about this work or would like to speak with a member of the project team, please contact us via email moorebank@tsamgt.com
or by phone 1800 986 465 (24/7).