M5 Ramp Closure & Traffic Switch July 2025
Current Works
Wednesday 2nd July 2025
Where and when
Moorebank Avenue Upgrade
Moorebank Avenue and Anzac Road Intersection 24-hour work:
• 25-28 July, weather permitting. (Contingency 1-4 August)
M5 exit ramp closure at Moorebank Avenue:
• 9pm Saturday 26 July to 6:30am Sunday 27 July
• 9pm Sunday 27 July to 5am Monday 28 July
As part of the Moorebank Intermodal Precinct project, during July pavement work will take place on Moorebank Avenue and the intersection of Moorebank Avenue and Anzac Road as we switch to the final design configuration.
Project contractor, BMD Constructions, will be undertaking 24-hour pavement work to upgrade the Moorebank Avenue tie into the northern end and the Moorebank Avenue and Anzac Road Intersection.
We will be working 24 hours from:
• 7pm Friday 25 July to 5am Monday 28 July, weather permitting (Contingency 1-4 August)
M5 Moorebank Avenue exit ramps will be closed:
• 9pm Saturday 26 July to 6:30am Sunday 27 July
• 9pm Sunday 27 July to 5am Monday 28 July
This work has been scheduled outside of regular construction hours to minimise the impact to road users and local businesses.
We will be switching traffic at the intersection from Monday 28 July.
In the event this work cannot occur due to the weather, it will be undertaken during the same hours on the next weekend and any updates will be published on the project website.
What to expect
Moorebank Avenue between the M5 and Anzac Road will remain open under stop / slow traffic control.
During M5 Moorebank Avenue exit ramp closures, please follow visual messaging board for alternate access to Moorebank Avenue.
Work will involve saw cutting, excavating, road base installation and asphalt works, installing underground services that will require the use of construction vehicles, excavators, rollers, an asphalt paver, grader, compaction equipment, bogie trucks and lighting towers.
This work will create additional background noise and traffic delays, please avoid the area if possible. Access to emergency vehicles remains as usual. We apologise for any inconvenience this may cause.
Intersection changes
From Monday 28 July changes at the Moorebank Avenue and Anzac Road intersection include:
• New left turn slip lane from Moorebank Avenue to Anzac Road
• Additional northbound right turn lane from Moorebank Avenue to Anzac Road
• Additional southbound right turn lane from Moorebank Avenue to Bushmaster Avenue
• Additional westbound lane from Anzac Road to Bushmaster Avenue with two dedicated right turn lanes into Moorebank Avenue
• Additional westbound lane on Bushmaster Avenue from Moorebank Avenue
• Additional eastbound lane at on Anzac Road from Moorebank Avenue
Keeping you updated
Work notifications are published on the project website at www.moorebank.au
We encourage community members and interested stakeholders to register for project updates to receive notification updates by email. Please contact our Community Relations team on the details below or opt-in for emailed updates by completing the form on our website.
Contact us
We appreciate your cooperation and patience while these important works are undertaken. If you have any queries about this work or would like to speak with a member of the project team, please contact us via email moorebank@tsariley.au or by phone 1800 986 465 (24/7).