Helicopter lifting works: Rescheduled to Saturday 8 July 2023

Current Works
Thursday 15th June 2023
Helicopter lifting works previously scheduled to occur at Moorebank Intermodal Precinct on Saturday 1 July during standard construction hours will now occur on Saturday 8 July between 8am and 1pm, weather permitting.

Project contractor Hansen Yuncken will use a helicopter to lift mechanical equipment from the staging area to the roof space on Warehouse 7 located at Moorebank Precinct East (east of Moorebank Avenue).

Refuelling if required, will be conducted in the staging area. Works will be carried out in accordance with the MPE 2 Consent and approved Construction Noise and Vibration Management Plan.

Any changes to this scheduled lift will be notified on this website.

What to expect

This work will create additional background noise during normal construction hours.

Moorebank Avenue will remain open at all times. Any traffic movement associated with the helicopter lifting activity will be minimal. We apologise for any inconvenience this may cause.

Where and when

Moorebank Precinct East
Saturday 8 July, standard construction hours,
8am – 1pm, weather permitting.

Any changes to this scheduled lift will be notified on this website.

Keeping you updated

Work notifications are published on this website.

We encourage community members and interested stakeholders to register to receive project updates by email. Please contact our Community Relations team on the details below or opt-in for email updates by completing the form on this website.

Contact us

We appreciate your cooperation and patience while these important works are undertaken.

If you have any queries about this work or would like to speak with a member of the project team, please contact us via email moorebank@tsamgt.com
or by phone 1800 986 465 (24/7).

Recent Media Releases
  • Media Releases, General News

  • 6 June 2024

Military Working Dogs honoured at Moorebank Intermodal Precinct

Helicopter lifting works previously scheduled to occur at Moorebank Intermodal Precinct on Saturday 1 July during standard construction hours will now occur on Saturday 8 July between 8am and 1pm, weather permitting. Project contractor Hansen Yuncken will use a helicopter to lift mechanical equipment from the staging area to the roof space on Warehouse 7 […]

Read More
  • 10 April 2024

Out of hours work – April to June 2024

Helicopter lifting works previously scheduled to occur at Moorebank Intermodal Precinct on Saturday 1 July during standard construction hours will now occur on Saturday 8 July between 8am and 1pm, weather permitting. Project contractor Hansen Yuncken will use a helicopter to lift mechanical equipment from the staging area to the roof space on Warehouse 7 […]

Read More
  • 23 February 2024

Out of hours work and traffic changes from 15 March 2024

Helicopter lifting works previously scheduled to occur at Moorebank Intermodal Precinct on Saturday 1 July during standard construction hours will now occur on Saturday 8 July between 8am and 1pm, weather permitting. Project contractor Hansen Yuncken will use a helicopter to lift mechanical equipment from the staging area to the roof space on Warehouse 7 […]

Read More