Continuing concrete pours on Moorebank Avenue

Current Works
Thursday 28th April 2022

Out of Hours work will continue to be carried out at SIMTA’s Moorebank Intermodal Terminal worksite until July due to recent weather that has delayed planned activities.

SIMTA contractor BMD Constructions will continue pouring concrete alongside Moorebank Avenue as part of the Moorebank Intermodal Terminal development. This work involves pouring concrete with an agitator, concrete pump and powered tools.

Work will take place near Anzac Road intersection.

Work is scheduled Monday to Friday until 1 July, weather permitting and excluding public holidays.

Work hours are from 5am to 7am and 6pm to 9pm. This work has been scheduled outside of regular construction hours to allow time for large pours to be completed.

Moorebank Avenue will remain open at all times.

Recent Media Releases
  • Current Works

  • 8 December 2023

Helicopter lifting works 9 December rescheduled to 13 and 20 January 2024

Out of Hours work will continue to be carried out at SIMTA’s Moorebank Intermodal Terminal worksite until July due to recent weather that has delayed planned activities. SIMTA contractor BMD Constructions will continue pouring concrete alongside Moorebank Avenue as part of the Moorebank Intermodal Terminal development. This work involves pouring concrete with an agitator, concrete […]

Read More
  • 1 December 2023

Helicopter lifting works – Saturday 9 December 2023

Out of Hours work will continue to be carried out at SIMTA’s Moorebank Intermodal Terminal worksite until July due to recent weather that has delayed planned activities. SIMTA contractor BMD Constructions will continue pouring concrete alongside Moorebank Avenue as part of the Moorebank Intermodal Terminal development. This work involves pouring concrete with an agitator, concrete […]

Read More
  • General News

  • 20 November 2023

Expressions of Interest Open for MIP Community Consultative Committee

Out of Hours work will continue to be carried out at SIMTA’s Moorebank Intermodal Terminal worksite until July due to recent weather that has delayed planned activities. SIMTA contractor BMD Constructions will continue pouring concrete alongside Moorebank Avenue as part of the Moorebank Intermodal Terminal development. This work involves pouring concrete with an agitator, concrete […]

Read More