  • Current Works
  • 12 December 2023

Oversized Vehicle Delivery – Wednesday 13 December 2023

There will be oversized vehicles arriving at Moorebank Intermodal Precinct on Wednesday 13 December 2023 between 4.30 am and 6 am.     What to Expect Project contractor John Holland will be accepting an oversized plant...

Read More
  • Current Works
  • 8 December 2023

Helicopter lifting works 9 December rescheduled to 13 and 20 January 2024

Helicopter lifting works previously scheduled to occur at Moorebank Intermodal Precinct on Saturday 9 December will now occur on Saturday 13 and Saturday 20 January 2024, between 8 am and 1 pm, weather permitting.   The...

Read More
  • 1 December 2023

Helicopter lifting works – Saturday 9 December 2023

Moorebank Intermodal Precinct contractors will be carrying out helicopter lifting works on Saturday 9 December during standard construction hours between 8 am and 1 pm, weather permitting.     The work will involve short helicopter lifts...

Read More
  • General News
  • 20 November 2023

Expressions of Interest Open for MIP Community Consultative Committee

Nominations are open for the appointment of a community member to the Moorebank Intermodal Precinct (MIP) Community Consultative Committee.   stakeholder group representative nomination form local community representative nomination form   The committee provides a forum...

Read More
  • 26 October 2023

Out of Hours Works on 30 October – 6 November 2023

As part of the Moorebank Intermodal Precinct project, out of hours works will commence on 30 October – 6 November 2023.   Project contractor, John Holland Rail, will be undertaking rail lengths movement at Moorebank Precinct...

Read More
  • 26 October 2023

Out of Hours works 26 and 27 October 2023 rescheduled for 30 and 31 October 2023 due to inclement weather

As part of the Moorebank Intermodal Precinct project, out of hours works initially scheduled for 26 and 27 October will commence on 30 and 31 of October 2023.   Project contractor, Direct Metal Roofing, will be...

Read More
  • 17 October 2023

Out of Hours works 19, 26 and 27 October 2023 rescheduled for 20, 26 and 27 October 2023 due to inclement weather

As part of the Moorebank Intermodal Precinct project, out of hours works initially scheduled for 19, 26 and 27 October will commence on 20, 26 and 27 of October 2023.   Project contractor, Direct Metal Roofing,...

Read More
  • 13 October 2023

Out of Hours Works on 16 October 2023

As part of the Moorebank Intermodal Precinct project, out of hours works will commence on 16 October 2023.   Project contractor,  Haines Bros, will be undertaking oversize deliveries of plants to Moorebank Precinct West. Extended works...

Read More
  • 12 October 2023

Out of Hours Works on 19, 26 and 27 October 2023

As part of the Moorebank Intermodal Precinct project, out of hours works will commence on 19, 26 and 27 of October 2023.   Project contractor, Direct Metal Roofing, will be undertaking oversize deliveries of roof sheeting...

Read More