MPW S4 Kmart Concrete Pours – Out of Hours Work Protocol
Thursday 25th September 2025
As part of the ongoing works at the future MPW S4 – Kmart Omnichannel Fulfillment Centre, out of hours works will need to be done by Richard Crookes Construction starting from October 2025.
Where and When:
Location: Bushmaster Avenue South
Dates: October 2025 – September 2026
Work Hours:
Evenings 6pm to 10pm Monday to Friday
Night 10pm to 7am Monday to Saturday
Afternoons 1pm to 6pm Saturday
What to Expect:
Concrete trucks, pumps, and supporting equipment (such as concrete finishing equipment and day makers) will mobilise to site outside normal working hours. Trucks and equipment will access the site Via. Moorebank Avenue and Bushmaster Avenue, entering the S4 (Kmart) site.
Concrete placement and finishing works will commence from early morning (outside of typical working hours).
Keeping You Updated:
Work notifications are published at moorebankintermodalprecinct.com.au
To receive email updates, please register via the form on our website or contact our Community Relations team.
Contact Us:
We appreciate your patience while these important works are underway. For more information, or to speak with a member of the project team:
• Website: moorebankintermodalprecinct.com.au
• Email: moorebank@tsamgt.com
• Phone: 1800 986 465 (24/7)
Recent Media Releases

Information Memorandum
Find out more
View Leasing Opportunities
Learn
Community Information
Discover